Medical projects since 2023
Prime Renovations builds and renovates medical offices in Baltimore City and the surrounding counties. The projects below are described by type and town; apart from FastMed, which is already on our work page, practice names are left out, and references are available on request.
An urgent care and primary care clinic in Pikesville (2023–2024). The space at Greenspring Shopping Center had been a bank branch, vault included. After demolition of the bank interior, Prime framed and finished a clinic of about 3,000 square feet: exam rooms numbered one through ten, a lab, reception and waiting, a kitchen, two offices and restrooms. The slab was cut for new waste lines, every exam room got its sink and dedicated circuits, the HVAC was reworked for clinical use, and the finishes, ceilings and ADA restrooms went in through 2023. The county closed the alterations permit with inspections passed. The full story and photographs are on the FastMed project page.
A behavioral-health therapy center in Lutherville-Timonium (2025). Two suites in an existing commercial building, built out for a regional behavioral-health provider opening a new center: framing, electrical, flooring and paint, then the closeout sequence an occupied medical building requires. Opening waited on the fire-alarm acceptance test, which passed in December 2025 after a device-synchronization problem was corrected, and the county's fire use-and-occupancy inspection passed the same day.
A primary and urgent care suite in Lutherville-Timonium (2024–2025). An interior alteration of an existing suite in the same building: new metal-stud partitions, floor leveling and new flooring with cove base, electrical rough-in and finish, and plumbing groundwork taken through county inspection.
A medical office suite in Towson (2025–2026). A physician's suite in a medical office building near the hospital campus, taken from an existing interior to a finished office; plans and photographs will be added.
A clinic refresh in East Baltimore (2024). Flooring, painting and interior repairs for a working medical clinic, finished in four to five weeks.
Repairs inside skilled-nursing facilities (2024–2026). Emergency ceiling, temporary-wall and structural shoring repairs inside an occupied skilled-nursing facility in Potomac, scheduled around residents and staff; and exterior porch and deck repair and painting at a facility in Westminster, where Prime worked as a subcontractor to the facility's general contractor.
What a medical build-out involves
Plumbing. A sink in every exam room, usually a lab or utility sink, and the drain and supply routes to serve them, which in a retail shell means cutting the slab.
Air. Clinical spaces need more air changes than offices, and some rooms need pressure relationships to their neighbors; equipment adds heat. The HVAC is designed for the use, not reused from the retail tenant before.
Electrical. Dedicated circuits for diagnostic and imaging equipment, and often more panel capacity than the space came with.
Medical gas. Oxygen and nitrous where the practice uses them, installed and tested to the applicable standard.
Accessibility. ADA-compliant routes, exam rooms with transfer space, accessible restrooms and reception counters.
Finishes. Floors and walls that take daily disinfection, with the details that keep cleaning simple.
Life safety and permits. Fire alarm, exits and extinguishers to the codes Maryland has adopted; building, plumbing, electrical and mechanical permits; in Baltimore County, a change-of-occupancy review for health-care use; and the certificate of occupancy. Licensed facility types, such as ambulatory surgical facilities and nursing homes, also go through the Maryland Department of Health's plan review; most physician offices do not. Our urgent care compliance guide covers the Baltimore specifics.
How a medical project runs
- Walk the space before you sign the lease. Slab, ceiling height, panel capacity, water service and plumbing routes decide how expensive a conversion will be.
- Plan around your workflow and equipment. Exam-room count, lab and imaging needs, and the equipment list set the plumbing and electrical scope.
- A written pro-forma estimate with line items, allowances and assumptions. How we estimate.
- Design, engineering and permits.
- Construction. In an operating clinic, we phase the work by room and schedule noisy work around patient hours.
- Closeout. Inspections, certificate of occupancy and the punch list.
What medical build-outs cost and how long they take
Our urgent care and primary care build-out of about 3,000 square feet came to roughly $95 per square foot in construction cost, with construction running through one calendar year and design and approvals before it. Suite fit-outs have run six to eight months, and a clinic refresh of flooring, paint and interior repairs took four to five weeks. These figures cover construction only; medical equipment, furniture and IT are separate.
Where we work
We work in Baltimore City and Baltimore, Howard, Anne Arundel and Carroll counties. Recent medical projects were in Pikesville, Towson, Lutherville-Timonium and East Baltimore, with facility repairs in Potomac and Westminster.
Common questions
What does a medical office build-out cost in Baltimore?
On Prime's projects, a full urgent care build-out of about 3,000 square feet came to roughly $95 per square foot in construction cost. The slab plumbing, HVAC and electrical capacity of the space drive most of the variation; a suite fit-out or a refresh of an existing clinic costs a fraction of a full build-out.
How long does it take?
About a year of construction for a full clinic build-out, with design and permits before it; six to eight months for a suite fit-out; and four to six weeks for a refresh.
Can we keep seeing patients during a renovation?
Usually. We phase the work by exam room and schedule noisy work around your hours.
What permits and inspections are involved?
A building permit with plumbing, electrical and mechanical trades; fire-alarm and fire-marshal inspections; in Baltimore County, a change-of-occupancy review for health-care use; and a certificate of occupancy. Licensed facility types have a state plan review as well.
Do you work inside operating healthcare facilities?
Yes. We have done emergency ceiling and structural shoring repairs inside an occupied skilled-nursing facility, and exterior repairs at another as a subcontractor.
Do you build dental offices?
Yes, six since 2023. See dental office construction.
Sources
- U.S. Department of Justice — 2010 ADA Standards for Accessible Design
- Facility Guidelines Institute — Guidelines for Design and Construction of health care facilities
- Baltimore County — change of occupancy permit (healthcare, assisted living and food service reviews)
- Maryland Department of Health — Office of Health Care Quality
- Maryland Department of Labor — current adopted building codes (IBC/IEBC/IRC/IECC 2021, NFPA 1 & 101 2024, MAC 2019)
Reviewed by Rodney Hakimi, MHIC #143153 · Published November 9, 2026